Unliquidated damages
Unliquidated damages are damages that are payable for a breach of contract, the exact amount of which has not been pre-agreed. This is in contrast with liquidated damages which are a pre-agreed when the contract is entered into.
Construction contracts generally include a provision for the contractor to pay liquidated damages (or liquidated and ascertained damages, sometimes referred to as LADs) to the client in the event of a breach of contract - typically failing to complete the construction works by the completion date set out in the contract.
Unliquidated damages are a form of compensation which is said to be ‘at large’, that is, the amount is not predetermined with the contract is entered into, but is determined by a court (either a judge or jury) after the breach has occurred.
The advantage of unliquidated damages is that it allows for the recovery of losses that may have been impossible to foresee or to estimate with any certainty before the breach.
The disadvantage is that it leaves the client having to prove their actual losses in the event of a breach, which can be very complex, and it leaves the contractor with an unknown liability.
The client must also prove that losses flow naturally from the breach and are not 'remote'.
In standard form construction contracts, parties will sometimes insert ‘NIL’ or ‘n/a’ for the rate for liquidated damages, if they do not wish to claim liquidated damages, however, this can imply that losses for unliquidated damages are also nil. If parties wish to exclude liability for liquidated damages, they must state this clearly in the contract to avoid ambiguity, either stating that unliquidated damages apply, or deleting the clause altogether.
[edit] Related articles on Designing Buildings Wiki
- Assignment.
- Breach of contract.
- Collateral warranty.
- Completion date.
- Damages in construction contracts.
- Dunlop Pneumatic Tyre Co Ltd v New Garage and Motor Co Ltd.
- Liquidated damages.
- Liquidated v unliquidated damages.
- Measure of damages.
- Practical completion.
- Remoteness.
- Substantial and other damages.
- The distinction between liquidated damages clauses and penalty clauses.
Featured articles and news
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.